National Children's Hospital Expenditure

Dáil Éireann Debate, Wednesday - 19 December 2018

Wednesday, 19 December 2018

Ceisteanna (418)

Stephen Donnelly

Ceist:

418. Deputy Stephen S. Donnelly asked the Minister for Health the reason for the significant increase in costs for the new children's hospital; and if he will make a statement on the matter. [54032/18]

Amharc ar fhreagra

Freagraí scríofa

The children’s hospital is one of the most complex and important public capital projects that this country has ever embarked upon. Considerable work has been undertaken on the project since April 2017 when Government gave the green light for the construction of the hospital. Enabling works on the main hospital site are complete and Phase A construction works (substructure works on the main site), which commenced in October 2017, are also now nearing completion. Following yesterday's decision, the Phase B 7-storey above ground works will begin early next year. Development is also well advanced on the paediatric outpatients and urgent care centres. Works at Connolly are on target for practical completion of the building in Spring 2019 with the opening scheduled for July 2019. Works at Tallaght are underway with a target handover date of July 2020, and the main hospital to be completed in 2022. The hospital will facilitate the implementation of a new model of care that will have a profound impact on all paediatric services once the new hospital is open.

At an early stage in the process, it was determined that the traditional method of procurement was not suitable or realistic for a project of this size and complexity. Accordingly, the contract is subject to a two-stage process with stage one consisting of a scope refinement and value engineering process, based upon tendered rates, to finalise the Phase B works (above ground). This approach allowed the early phases of work to commence on site while also allowing for the detail of later phases to be finalised and agreed. This approach brings issues on cost to the fore much earlier in the life of the project than is the case where traditional procurement approaches are deployed.

Following the evaluation by the National Paediatric Hospital Development Board in early 2017 of main construction tenders and the selection of preferred contractors, the final cost of the design, build and equipment programme for which the NPHDB is responsible was €983m. Following the completion of the second stage of the two-stage tender procurement process, the project cost is now at €1,433 million, an increase of €450 million.

Of the €450m additional costs, construction costs account for €319m. The balance of €131m, which includes €50m in VAT, relates to costs associated with staff, consultants, planning, design team fees, risk/contingency, and Management Equipment Service.

As I have already stated the increased cost is a matter of great concern and I have made it clear that Phase B of the construction project must be delivered within budget and timescale. Accordingly, there will be an independent review of the escalation in cost in determining the adjusted contract sum, the contributory factors and associated responsibilities so that any potential weaknesses are identified and comprehensively and speedily resolved in the interests of the successful completion of the project and the effective management of public funds. The National Paediatric Hospital Development Board will be required to provide on-going assurance to the HSE, Department of Health and Government that Phase B of the project is being delivered within budget and timescale.