Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 15 January 2019

Tuesday, 15 January 2019

Ceisteanna (348)

Fergus O'Dowd

Ceist:

348. Deputy Fergus O'Dowd asked the Minister for Education and Skills the status of the proposed special school for County Louth that will merge schools (details supplied); the reason for the significant delays in the project; and if he will make a statement on the matter. [1080/19]

Amharc ar fhreagra

Freagraí scríofa

A building project which involves 2 new replacement school buildings on a single campus greenfield site for the schools referred to by the Deputy is included in my Department’s 6 year Construction Programme.

A project brief was finalised in late December and the project will be delivered via the ADAPT programme. The ADAPT programme uses a professional external Project Manager to coordinate and drive the respective design teams on each project.

In this regard, a tender competition is in train to establish a Project Manager framework which is expected to be in place by early March. The formulation of tender documentation is underway and once the framework has been established a tender exercise will be carried out to appoint a Project Manager for this particular project.

All schools with projects on the ADAPT programme will be contacted shortly by my Department to provide an update on the status of their respective project. I wish to confirm to the Deputy that my Department is committed to providing a new school building for the school in question.

Barr