School Accommodation Provision

Dáil Éireann Debate, Tuesday - 5 February 2019

Tuesday, 5 February 2019

Ceisteanna (223, 224)

John Curran

Ceist:

223. Deputy John Curran asked the Minister for Education and Skills if a progress report on the provision of an extension for a school (details supplied) in County Dublin will be provided; and if he will make a statement on the matter. [5091/19]

Amharc ar fhreagra

John Curran

Ceist:

224. Deputy John Curran asked the Minister for Education and Skills if a progress report on the provision of an extension for a school (details supplied) in County Dublin will be provided; and if he will make a statement on the matter. [5092/19]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 223 and 224 together.

The major building project for the schools referred to by the deputy is currently at an advanced stage of Architectural Planning, Stage 2b - Detailed Design, which includes the application for statutory approvals and the preparation of tender documents. All statutory approvals have been secured. The schools share the same site and the building project will be delivered as a joint project.

The schools and their Design Team have submitted a Brief Change Report to my Department which is currently under review. A response will issue shortly.

Barr