Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 12 February 2019

Tuesday, 12 February 2019

Ceisteanna (237)

Fiona O'Loughlin

Ceist:

237. Deputy Fiona O'Loughlin asked the Minister for Education and Skills his plans for the proposed extension of a school (details supplied); the status of the project; the timeline for completion of the works; and if he will make a statement on the matter. [6364/19]

Amharc ar fhreagra

Freagraí scríofa

The process of Pre-Qualification of contractors for the project in question is under way. The Pre-qualification process culminates in the compilation of shortlists of suitable candidates for each respective discipline.

The draft pre-qualification report was submitted to my Department for review in January 2019. The Department has issued comments to be actioned by the Design Team with regard to finalising the process.

When this review is complete the project will then be progressed to tender stage, which normally takes between 7 and 8 months to complete.

This project is included in the Department of Education and Skills' six-year construction programme.