Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

National Children's Hospital Expenditure

Dáil Éireann Debate, Tuesday - 12 February 2019

Tuesday, 12 February 2019

Ceisteanna (381)

Joan Collins

Ceist:

381. Deputy Joan Collins asked the Minister for Health the cost of the original agreed tender with a company (details supplied) for the children’s hospital in St. James's; and the amount it has increased to. [6402/19]

Amharc ar fhreagra

Freagraí scríofa

Contract tenders were received from the main contractor, mechanical and electrical installation contractors and lift contractors in October 2016. The most competitive tender sum, excluding VAT, in total was €637m, of which €432m applied to the main contractor.

Following completion of the Guaranteed Maximum Price Process (GMP) in November 2018, the total adjusted GMP construction budget is €890m excluding VAT, of which €556m applies to the main contractor.