Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 26 March 2019

Tuesday, 26 March 2019

Ceisteanna (280)

Brendan Ryan

Ceist:

280. Deputy Brendan Ryan asked the Minister for Education and Skills if a contract has been awarded for the supply of temporary prefabricated accommodation for ten new start-up schools which are due to open in September 2019; and if he will make a statement on the matter. [12711/19]

Amharc ar fhreagra

Freagraí scríofa

I can confirm that the Department's Project Manager has tendered for the supply of temporary accommodation for 10 new start-up schools for September 2019. The Letter of Acceptance has issued to the chosen accommodation providers.