124. Deputy Eugene Murphy asked the Minister for Communications, Climate Action and Environment when broadband service will be available under the National Broadband Plan at the home of a person (details supplied). [23072/19]

Amharc ar fhreagra

Eugene Murphy

Ceist:

125. Deputy Eugene Murphy asked the Minister for Communications, Climate Action and Environment when broadband service will be available under the National Broadband Plan at a location (details supplied). [23077/19]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 124 and 125 together.

Both premises referenced by the Deputy are in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie The AMBER areas represent the target areas for the proposed State led Intervention under the NBP.

This intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network. Following rigorous evaluation by my Department, I recently brought a recommendation to Government to confer Preferred Bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process and Government agreed to this at its meeting on 7 May.

The Government Decision of 7 May 2019 means that it is intended to award the State Intervention contract to the Bidder. This award is subject to contract close including finalisation of financial and legal documents. Deployment of the NBP State Intervention network will commence shortly after that. The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment

In the first year of this roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations. A deployment plan will be made available by the bidder once the contract is signed. The Bidder is aiming to pass 133,000 premises by end of the second year of the overall deployment, with 70-100,000 passed each year thereafter until roll out is completed.