83. Deputy Martin Heydon asked the Minister for Education and Skills the progress of a new school building for a school (details supplied) in County Kildare; and if he will make a statement on the matter. [24688/19]

Amharc ar fhreagra

Freagraí scríofa

The major building project for this school is at an advanced stage of architectural planning, Stage 2b - Detailed Design, which includes the applications for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents. All statutory approvals have been obtained.

Following a legal challenge, authorisation to re-commence the pre-qualification process issued to the Design Team and school. This advert has recently closed and the Design Team is currently in the process of compiling a shortlist of contractors for tender stage. 

When the pre-qualification process for the main contract and reserved specialists contracts is complete, the project will then be progressed to tender stage.

A tender stage normally takes between 7 and 8 months to complete.