Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 9 July 2019

Tuesday, 9 July 2019

Ceisteanna (260)

Fiona O'Loughlin

Ceist:

260. Deputy Fiona O'Loughlin asked the Minister for Education and Skills the timeline for the construction of the new permanent building following the amalgamation two schools (details supplied) in view of the fact that planning permission has been granted; and if he will make a statement on the matter. [29800/19]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is at an advanced stage of architectural planning Stage 2b (Detailed Design), which includes the application for statutory approvals and the preparation of tender documents. All statutory approvals have been secured.

The Design Team has confirmed that it is working on finalising the Stage 2b report ensuring it will be a "Near Zero Energy Building" (NZEB) in compliance with the 2017 amendment to Part L of the current Building Regulations.

Upon completion, receipt and review of the Stage 2(b) submission, my Department will be in contact with the school regarding the progression of the project at that time.