Better Energy Homes Scheme

Dáil Éireann Debate, Tuesday - 23 July 2019

Tuesday, 23 July 2019

Ceisteanna (2168, 2172, 2173, 2174, 2178, 2227, 2234, 2273, 2281)

Seán Sherlock

Ceist:

2168. Deputy Sean Sherlock asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has now ceased; if this is as a result of reaching the allocated budget; if so, the measures he plans to take to ensure that skilled staff are not made redundant or community based organisations are forced to close down; his views on whether such actions would have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits per annum; and if he will make a statement on the matter. [31616/19]

Amharc ar fhreagra

Alan Kelly

Ceist:

2172. Deputy Alan Kelly asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has now ceased; if this is as a result of reaching the allocated budget; if so, the measures he plans to take to ensure that skilled staff are not made redundant or community based organisations are forced to close down; his views on whether such actions would have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits per annum; and if he will make a statement on the matter. [31640/19]

Amharc ar fhreagra

Brendan Ryan

Ceist:

2173. Deputy Brendan Ryan asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has now ceased; if this is as a result of reaching the allocated budget; if so, the measures he plans to take to ensure that skilled staff are not made redundant or community based organisations are forced to close down; his views on whether such actions would have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits per annum; and if he will make a statement on the matter. [31641/19]

Amharc ar fhreagra

Seán Sherlock

Ceist:

2174. Deputy Sean Sherlock asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has ceased; if this is a result of reaching the allocated budget; if so, the measures he plans to take to ensure that skilled staff are not made redundant or community based organisations are forced to close; his views on whether such actions would have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits annually; and if he will make a statement on the matter. [31650/19]

Amharc ar fhreagra

Brendan Howlin

Ceist:

2178. Deputy Brendan Howlin asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has now ceased; if this is as a result of reaching the allocated budget; if so, the measures he plans to take to ensure that skilled staff are not made redundant or community based organisations are forced to close down; his views on whether such actions will have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits per annum; and if he will make a statement on the matter. [31855/19]

Amharc ar fhreagra

Willie Penrose

Ceist:

2227. Deputy Willie Penrose asked the Minister for Communications, Climate Action and Environment the reason the allocation of homes for retrofitting to community based organisations under the SEAI better energy warmer homes scheme has now ceased; if this is as a result of reaching the allocated budget; if so, the measures he plans to take to ensure skilled staff are not made redundant or community based organisations are forced to close down; his views on whether such actions would have a detrimental impact on building capacity within the sector to achieve the Project Ireland 2040 objective of 45,000 domestic retrofits per annum; and if he will make a statement on the matter. [32499/19]

Amharc ar fhreagra

Richard Boyd Barrett

Ceist:

2234. Deputy Richard Boyd Barrett asked the Minister for Communications, Climate Action and Environment if his attention has been drawn to the fact that some community based organisations that were delivering quality energy retrofits to households living in fuel poverty are idle due to an apparent funding shortage at the SEAI, which has resulted in all work allocations to community based organisations being ceased, which could also result in significant job losses of a skilled workforce in view of the launch of the Climate Action Plan 2019, which includes plans to retrofit 500,000 homes; and if he will make a statement on the matter. [32751/19]

Amharc ar fhreagra

Anne Rabbitte

Ceist:

2273. Deputy Anne Rabbitte asked the Minister for Communications, Climate Action and Environment the reason community based organisations are not being allocated work under the SEAI better energy warmer homes scheme; if funding of such work for community based organisation has ceased; if his Department has considered measures to avoid job redundancies as a result of the ceasing of allocations; his plans to fulfil the commitment to have 50,000 homes retrofitted per annum as per the Climate Action Plan 2019; and if he will make a statement on the matter. [33495/19]

Amharc ar fhreagra

Danny Healy-Rae

Ceist:

2281. Deputy Danny Healy-Rae asked the Minister for Communications, Climate Action and Environment the steps being taken on the shortage in funding under the SEAI better energy warmer home scheme, which has meant ceasing work allocations to community based organisations; and if he will make a statement on the matter. [33912/19]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 2168, 2172 to 2174, inclusive, 2178, 2227, 2234, 2273 and 2281 together.

The Better Energy Warmer Homes Scheme provides free energy efficiency upgrades to the homes of people living in or at risk of energy poverty. The Scheme is administered by the Sustainable Energy Authority of Ireland (SEAI) on behalf of my Department.

In June 2018 the range of energy efficiency measures available under the Warmer Homes Scheme was expanded to include ‘deeper’ measures. Under the expanded scheme, in certain circumstances, external or internal wall insulation, central heating and replacement windows, can be provided where a technical assessment (by SEAI contractors) considers them necessary. These additional measures brought the level of retrofit into alignment with that envisaged by the National Development Plan, but changed the relative attractiveness of availing of other 'shallower' interventions. Managing the enhanced package of measures has required careful monitoring and programme management by SEAI within available resources.

The initial 2019 budget allocation for the Scheme of €24m was in line with the 2018 allocation. However, following a mid-year capital review conducted by my Department and SEAI, the budget has been increased to €39.8m for 2019. This will facilitate additional work allocations for CBOs and contractors in 2019 and the SEAI has in recent days been in communication with the CBOs in that regard.

The Warmer Homes Scheme is delivered through a panel of contractors, appointed through a competitive tendering process. Since the introduction of ‘deeper’ measures, some CBOs that are only contracted to carry out ‘shallow’ measures under the Warmer Homes Scheme, have seen their allocation volumes reduce. While the expansion of the scheme has been positive for the energy poor homeowners involved and for building capacity in the supply chain in general, it has had some negative impacts for contractors that are unable to deliver deeper works.

SEAI will be renewing its contract with Warmer Homes Scheme contractors in 2020, which will require all contractors to be able to deliver all measures, deeper and shallow. SEAI is encouraging all CBOs to apply for this contract and has been working with CBOs over the past year supporting them in upskilling and gaining experience to help ensure they can compete for the 2020 contract and that their organisations remain viable.

Building capacity in the sector is a top priority. However it is critical that we build capacity sustainably, ensuring that all contractors delivering these ever-increasingly complex retrofit projects are adequately skilled and resourced. The Climate Action Plan includes a number of measures which will build the supply chain for energy efficiency retrofits required to meet our 2030 targets including support for the development of necessary skills across the education and training system.