Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 23 July 2019

Tuesday, 23 July 2019

Ceisteanna (615)

Joan Burton

Ceist:

615. Deputy Joan Burton asked the Minister for Education and Skills the timeline for the delivery of a new permanent school buildings for schools (details supplied); when the new school buildings will open; and if he will make a statement on the matter. [34162/19]

Amharc ar fhreagra

Freagraí scríofa

A building project for the school referred to by the Deputy is included in my Department's Construction Programme which is being delivered under the National Development Plan.

The project is at an advanced stage of the tender process, and subject to no issues arising it is anticipated that works could commence in the final quarter of 2019, with an anticipated contract duration of 24 months.