Dáil Éireann Debate, Friday - 6 September 2019

Friday, 6 September 2019

Ceisteanna (1540)

Brendan Smith

Ceist:

1540. Deputy Brendan Smith asked the Minister for Communications, Climate Action and Environment the status of the procurement process in respect of the proposed North-South interconnector; if procurement is proceeding and planning applications not determined; and if he will make a statement on the matter. [36533/19]

Amharc ar fhreagra

Freagraí scríofa

EirGrid is the designated Transmission System Operator and its role includes the operation, maintenance and development of the electricity transmission network in Ireland. The construction of the North South Interconnector, and all related procurement activities, is an operational matter for EirGrid and ESB Networks and one in which I have no function.

I am advised that due to the very long lead times that can arise in relation to projects of this nature and the benefits of a single joint procurement process to be undertaken and managed by ESB Networks, EirGrid sought approval from the regulators in Ireland and Northern Ireland to commence procurement. Following this approval, in September 2017 ESB Networks commenced a number of procurement processes in relation to the project.

In June 2019 ESB Networks awarded a framework contract for the design, test and supply of steelwork in relation to the project. I am advised that the design and testing part of the contract will commence shortly. However under the framework there will be no supply of materials until the planning process in Northern Ireland is complete.