Schools Building Projects Status

Dáil Éireann Debate, Friday - 6 September 2019

Friday, 6 September 2019

Ceisteanna (407)

Darragh O'Brien

Ceist:

407. Deputy Darragh O'Brien asked the Minister for Education and Skills the status of the provision of a permanent school for a school (details supplied); and if he will make a statement on the matter. [35964/19]

Amharc ar fhreagra

Freagraí scríofa

This building project is currently at Stage 2B of the Architectural Planning process – Detailed Design Stage. The pre-qualification of contractors process has been carried out by the Design Team.  The next stage of Architectural Planning for this project will be Stage 3 – tender stage which normally takes 7-8 months to complete. My Department will be in contact with the school regarding progression to tender stage.

This building project is included in my Department’s Construction Programme which is being delivered under the National Development Plan.