National Broadband Plan Implementation

Dáil Éireann Debate, Tuesday - 22 October 2019

Tuesday, 22 October 2019

Ceisteanna (514)

Michael Lowry

Ceist:

514. Deputy Michael Lowry asked the Minister for Communications, Climate Action and Environment the status of e-fibre broadband to a premises (details supplied) which is subject to the provision of the State-led intervention under the national broadband plan; when it is envisaged that e-fibre broadband will be available at this location; the status of the deployment of the national broadband plan in County Tipperary; and if he will make a statement on the matter. [43590/19]

Amharc ar fhreagra

Freagraí scríofa

Every home, farm, school and business in Ireland will have access to high speed broadband – no matter where they are located – following the Government’s decision to approve the appointment of a preferred bidder to the National Broadband Plan. Under this plan, Ireland will become one of the first countries in the world to ensure that those in rural areas have the same digital opportunities as those in urban areas. The specific premises referenced by the Deputy is in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie . The AMBER areas represent the target areas for the proposed State led Intervention under the NBP.

With regard to Co Tipperary the table below sets out, as of Quarter 2 2019, the number of premises in Co Tipperary where access to a high speed broadband connection is, or will be, delivered by commercial operators (BLUE/LIGHT BLUE) and those where access to this vital service will be delivered under the State led intervention (AMBER)

.

County

Premises within the NBP Intervention Area

Premises within Commercial Operator’s Area

Premises within eir planned rural deployment

Total

Tipperary

30,306 (36.07%)

50,816 (60.47%)

2,909 (3.46%)

84,031

Since the Government decision in May 2019 to appoint NBI as the Preferred Bidder for the National Broadband Plan contract, work has continued on the due diligence necessary to conclude the contract. This process is progressing towards contract award, which is expected before the end of the year. The network deployment will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment. A deployment plan will be made available by the Bidder once the contract is signed. In the first year of roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll out is completed.

Work continues on finalising the contract and in parallel to this work, I am considering the recommendations of the Joint Oireachtas Communications Committee report which was published recently. I will bring my deliberations of the report to Government in due course.