Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 12 November 2019

Tuesday, 12 November 2019

Ceisteanna (191)

John Lahart

Ceist:

191. Deputy John Lahart asked the Minister for Education and Skills when construction will commence on the new building for a school (details supplied); and if he will make a statement on the matter. [46478/19]

Amharc ar fhreagra

Freagraí scríofa

The procurement process for a bundle of projects is due to commence shortly with the publication of a contract notice to determine a shortlist of interested contractors. The permanent building for the school referred to by the Deputy is part of this bundle of projects.

The procurement process (and the associated tendering to short-listed contractors) for this bundle of projects will be ongoing during Q4 2019 and Q1 2020.

It is anticipated that construction of this school building project will commence in Q2 2020.