Dáil Éireann Debate, Wednesday - 13 November 2019

Wednesday, 13 November 2019

Ceisteanna (200)

Kevin O'Keeffe

Ceist:

200. Deputy Kevin O'Keeffe asked the Minister for Communications, Climate Action and Environment when high speed broadband will be made available in an area in which a business (details supplied) is in operation and recently had to close for the day owing to lack of broadband service. [46797/19]

Amharc ar fhreagra

Freagraí scríofa

The premises referenced by the Deputy is in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie. The AMBER areas represent the target areas for the proposed State led Intervention under the NBP. This intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network.

Since the Government decision in May 2019 to appoint NBI as the Preferred Bidder for the National Broadband Plan contract, work has continued on the due diligence necessary to conclude the contract. This process is progressing towards contract award, which is expected before the end of the year. The network deployment will commence shortly after that.

The Bidder has indicated that the network rollout will take an estimated 7 years from the beginning of deployment. A deployment plan will be made available by the Bidder once the contract is signed.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

A deployment plan will be made available by the Bidder once the contract is signed. In the first year of roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll out is completed.

Work continues on finalising the contract and in parallel to this work, I am considering the recommendations of the Joint Oireachtas Communications Committee report which was published recently. I will bring my deliberations of the report to Government in due course.