29. Deputy Louise O'Reilly asked the Minister for Public Expenditure and Reform the timeline for works on Rush Garda station; the date the station is scheduled to be reopened by; and if he will make a statement on the matter. [46889/19]

Amharc ar fhreagra

Freagraí scríofa

Following completion of the tender process at the end June 2019, works to re-open Rush Garda Station commenced and are now virtually completed. Minor snagging is underway and connection to the electricity service supplier is awaited. Once these are finalised over the coming weeks the building will be handed over to An Garda Síochána. 

It will be an operational matter for An Garda Síochána as to when the Station will be reopened.