156. Deputy Brendan Howlin asked the Minister for Education and Skills further to Parliamentary Question No. 95 of 24 October 2019, if stage one has been completed; if stage 2A has commenced; and if he will make a statement on the matter. [52108/19]

Amharc ar fhreagra

Freagraí scríofa (Ceist ar Education)

As the Deputy is aware, the delivery of the project for St. Farnan's Post Primary School has been devolved to Kildare and Wicklow Education and Training Board (KWETB).

The Stage 1 (preliminary design) process is ongoing and will need to be completed prior to the project commencing Stage 2A.