Dáil Éireann Debate, Tuesday - 17 December 2019

Tuesday, 17 December 2019

Ceisteanna (203)

Pat the Cope Gallagher

Ceist:

203. Deputy Pat The Cope Gallagher asked the Minister for Education and Skills the progress made on a school project (details supplied) in County Donegal; the timeline for the delivery of the new school building; when works will commence on site; if a budget is ring-fenced for same; and if he will make a statement on the matter. [53054/19]

Amharc ar fhreagra

Freagraí scríofa

A building project for the school referred to by the Deputy is included in my Department's Construction Programme which is being delivered under the National Development Plan.

The project is currently out to tender, with tenders due back in mid December. Once the tenders are returned the Design Team will prepare and submit a tender report to my Department for assessment. 

Subject to no issues arising, during the tender process it is envisaged that works should commence on site in the 2nd quarter of 2020, with a contract duration of approximately 18 months.