Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 17 December 2019

Tuesday, 17 December 2019

Ceisteanna (205)

Pat the Cope Gallagher

Ceist:

205. Deputy Pat The Cope Gallagher asked the Minister for Education and Skills the progress made on a school project (details supplied) in County Donegal; the timeline for the delivery of the project; and if he will make a statement on the matter. [53056/19]

Amharc ar fhreagra

Freagraí scríofa

The major building project for the school referred to by the deputy is at an advanced stage of architectural planning, Stage 2b (Detailed Design).  The Stage 2(b) submission has been reviewed by my Department and comments have issued to the school and its Design Team.

At the end of September the project was authorised to commence the pre-qualification of contractors’ process and this process is currently on-going. 

When pre-qualification is complete this project will then be progressed to tender stage.

A tender stage normally takes between 7 and 8 months to complete.

Barr
Roinn