Dáil Éireann Debate, Wednesday - 18 December 2019

Wednesday, 18 December 2019

Ceisteanna (367, 368, 370)

Robert Troy

Ceist:

367. Deputy Robert Troy asked the Minister for Communications, Climate Action and Environment the status of broadband availability for a property (details supplied). [53473/19]

Amharc ar fhreagra

Robert Troy

Ceist:

368. Deputy Robert Troy asked the Minister for Communications, Climate Action and Environment if a fibre broadband service will be provided to an area (details supplied) as part of the current Eir roll-out. [53474/19]

Amharc ar fhreagra

Robert Troy

Ceist:

370. Deputy Robert Troy asked the Minister for Communications, Climate Action and Environment if fibre broadband will be supplied to a property (details supplied). [53477/19]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 367, 368 and 370 together.

The National Broadband Plan (NBP) is the Government’s plan to rollout high speed broadband to the 1.1 million people living and working in the nearly 540,000 premises including almost 100,000 businesses and farms, along with 695 schools where commercial operators will not commit to deliver the service.

The Deputy's Questions relate to premises which are located in the AMBER area on the NBP High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie. The AMBER area represents the area to be served by the network to be deployed under the NBP State led Intervention, the contract for which was signed on 19 November with National Broadband Ireland (NBI).

Work has already begun and a deployment plan will be made available by NBI shortly. All counties will see premises passed in the first 2 years and over 90% of premises in the State will have access to high speed broadband within the next four years.

Approximately 300 Broadband Connections Points (BCPs), including schools, library hubs and local sports halls in every county in Ireland, will be connected to high speed broadband during 2020, to enable communities to quickly get free public access to high speed broadband. The BCP locations are available to view on the High Speed Broadband Map on the Department’s website www.dccae.gov.ie.

The BCPs have been specifically selected by the local authorities so that they can provide public Wi-Fi and other facilities to support mini digital/enterprise hubs to the local community in advance of the main NBP deployment. Broadband Officers in each Local Authority were tasked with consulting with local communities and business to find the appropriate mix of locations to reap the maximum benefits.

By the end of 2021, NBI plans to pass approximately 115,000 premises, with 70,000 - 100,000 passed each year thereafter until rollout is completed. NBI has indicated that the network rollout will take an estimated 7 years from the beginning of deployment.

Barr