Garda Station Refurbishment

Dáil Éireann Debate, Wednesday - 13 May 2020

Wednesday, 13 May 2020

Ceisteanna (333)

Louise O'Reilly

Ceist:

333. Deputy Louise O'Reilly asked the Minister for Justice and Equality the Garda stations within the north Dublin Garda division that are due for refurbishment in the first half of 2020; and the status of each project. [3956/20]

Amharc ar fhreagra

Freagraí scríofa

The resources allocated to An Garda Síochána have reached record levels, with an allocation of €1.88 billion for 2020. The capital allocation to An Garda Síochána has also been further increased to a total of €116.5million. This ongoing financial support is intended to enable a strong and visible police presence throughout the country, to maintain and strengthen community engagement, provide reassurance to the public and deter crime.

The Deputy will appreciate that the Office of Public Works has responsibility for the provision and maintenance of Garda accommodation. Works in relation to Garda accommodation are progressed by the Garda authorities working in close cooperation with the Office of Public Works (OPW).

I am informed by the Garda authorities and the OPW that a number of Garda stations within the DMR North Division are currently undergoing or are due some works in the period referred to by the Deputy.

I am advised by the Garda authorities and OPW that the refurbishment of Rush Garda Station, which has been undertaken as part of the Garda station pilot reopening project, has been completed, with the exception of the final connection to the ESB grid. The OPW expects to be in a position to hand over the Garda Station in the coming weeks. Following handover to An Garda Síochána, the internal fit out of the Garda Station, including furniture and ICT, will be required before the station is reopened.

I am further informed that additional office accommodation is being provided for Coolock Garda station. Two Portakabins previously used to accommodate Garda Legal Services in Garda Headquarters are undergoing a refurbishment, and will be used to provide that extra office accommodation. I am informed that these works are due for completion in the coming weeks.

Provision of temporary accommodation replace an existing modular building at Swords Garda station is also currently being progressed by the OPW in cooperation with the Garda authorities. I understand that this accommodation will provide office space and facilities for Gardaí assigned to that station.

I am further informed that works are ongoing for installation of two electric vehicle charging points at the rear of the Garda station at Dublin Airport. I am informed that this work is expected to be completed in the coming weeks.