Dáil Éireann Debate, Wednesday - 3 June 2020

Wednesday, 3 June 2020

Ceisteanna (118)

Niamh Smyth

Ceist:

118. Deputy Niamh Smyth asked the Minister for Public Expenditure and Reform the status of and the expected completion date for construction works at the new Garda station in Bailieborough, County Cavan; and if he will make a statement on the matter. [8335/20]

Amharc ar fhreagra

Freagraí scríofa

The pre-qualification procedures for the Main Contractor and Reserved Specialists is ongoing during the current Covid-19 restrictions.  We expect this to be completed early in Quarter 3, 2020.  It is also hoped that tender documentation will issue later in Quarter 3 2020, with a Contract expected to be in place before the end of 2020.  Construction work will take approx. 18 months to complete.