Flood Relief Schemes

Dáil Éireann Debate, Tuesday - 30 June 2020

Tuesday, 30 June 2020

Ceisteanna (100)

Pádraig O'Sullivan

Ceist:

100. Deputy Pádraig O'Sullivan asked the Minister for Public Expenditure and Reform the timeline for the resumption of the Glashaboy flood relief scheme, Glanmire, County Cork; the details of the latest delay; the estimated timeline for the resumption and completion of works; and if he will make a statement on the matter. [13251/20]

Amharc ar fhreagra

Freagraí scríofa

The Office of Public Works, under the provisions of the Arterial Drainage Acts, has submitted the proposal for the Glashaboy Flood Relief Scheme, accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS), to the Minister for Public Expenditure and Reform for formal Confirmation.

On foot of the European Union (Environmental Impact Assessment) (Arterial Drainage) Regulations 2019, which were published in Iris Oifigiúl on 27 September 2019, the Minister for Public Expenditure and Reform has undertaken an environmental assessment of the proposed scheme in line with required legislative requirements. This involved an independent assessment of the EIAR / NIS and a public consultation process.

On the 5 May 2020, the Office of Public Works received correspondence from the Department of Public Expenditure and Reform that the independent assessment is now complete. This correspondence has requested, pursuant to section 7(B) sub-section 4 of the 2019 European Union (Environmental Impact Assessment) (Arterial Drainage) Regulations, certain items of further information that are required to complete the process. My Office is currently preparing the additional information requested - which generally relates to further detail on the processes followed and assessments undertaken in developing the scheme - to be submitted to the Department in order that the assessment can be completed and the scheme confirmed by the Minister for Public Expenditure and Reform.  This information is currently scheduled to be provided to the Department no later than October 2020.

The procurement and appointment of a Contractor will be progressed for this scheme following formal Ministerial Confirmation.  The flood relief scheme will be funded from within the allocated €1 billion for flood risk management over the period 2018-2027. Provision for the cost of the Scheme is included in the Office of Public Works' multi annual capital allocation.

OPW is committed to funding this project and attends monthly steering meetings to offer every assistance to Cork City Council to ensure a contractor is engaged, and the works commence, as soon as possible.