Schools Building Projects

Dáil Éireann Debate, Tuesday - 21 July 2020

Tuesday, 21 July 2020

Ceisteanna (363)

Alan Farrell

Ceist:

363. Deputy Alan Farrell asked the Minister for Education and Skills the status of the delivery of a new school building and refurbishment of the existing school infrastructure for a school (details supplied); and if she will make a statement on the matter. [16471/20]

Amharc ar fhreagra

Freagraí scríofa

The building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.

This project is currently at Stage 1 of Architectural planning (Site Suitability, Site Report, and Initial Sketch Scheme). A Stage 1 Stakeholders meeting with the Design Team, Project Manager, and Board of Management and Department officials was held on 9th July 2020.

The Design Team is to prepare a revised sketch scheme option for review by my Department and the Project Manager. A further meeting will be arranged at that time.