Flood Relief Schemes

Dáil Éireann Debate, Wednesday - 22 July 2020

Wednesday, 22 July 2020

Ceisteanna (103)

Alan Dillon

Ceist:

103. Deputy Alan Dillon asked the Minister for Public Expenditure and Reform the status of progress of a flood relief scheme for Crossmolina, County Mayo; and his plans to review and expedite this timeline in view of the ongoing flood threat to the residents of the town. [17544/20]

Amharc ar fhreagra

Freagraí scríofa

The proposed flood relief scheme for Crossmolina, Co. Mayo, is progressing broadly in line with the current programme. Some delay has been experienced in recent months due to the consultants being unable to carry out the final environmental surveys during the nationwide Covid-19 shutdown. To minimise these delays, the project team worked to progress all other tasks that could be safely carried out, such as desk studies, and continuing work on the preparation of documentation that will be submitted to the Minister for Public Expenditure and Reform (MPER) for formal Confirmation of the scheme under the Arterial Drainage Act, 1945.

Since the easing of the Covid-19 restrictions, the consultants have carried out the final elements of the environmental surveys and the project team is now in the process of finalising the documentation for the Confirmation process. It is anticipated that the scheme will be submitted to MPER in Quarter 3 of this year.

Once submitted for Confirmation, the Minister will carry out an Environmental Impact Assessment as he is required to do which will involve an independent review of the Environmental Impact Assessment Report submitted with the scheme and the holding of a public consultation on the scheme. If the Minister Confirms the proposed scheme, the next stage in the process will be completion of the detailed design and the tender documents for the procurement of some specialist works contractors. It is planned that the main scheme works will be carried out by the OPW's direct labour force.

In order to expedite this timeline, the project team will commence the preparation of the tender documents in parallel with the Confirmation process. While some amendments to the tender documents may be required following the Confirmation process, it should be possible to progress with the procurement of contractors as soon as possible following Confirmation.

I wish to assure you that I am very aware of the concern of the residents and businesses of Crossmolina to have protection from flooding without further delays. The provision of effective flood defences to Crossmolina is a priority for me and for the Government. We want to ensure that the scheme that is built is technically and environmentally sound. I know that the OPW, Mayo County Council, and the scheme consultants have worked extremely hard to advance the scheme in what has been a complex environmental situation.