Electricity Grid

Dáil Éireann Debate, Tuesday - 28 July 2020

Tuesday, 28 July 2020

Ceisteanna (99)

Darren O'Rourke

Ceist:

99. Deputy Darren O'Rourke asked the Minister for Communications, Climate Action and Environment if his attention has been drawn to the fact that companies (details supplied) jointly requested and obtained approval from the regulators here and Northern Ireland for exceptional funding to commence an advanced procurement process prior to receipt of planning approval having signed procurement contracts without planning approval yet fully obtained; and if he will make a statement on the matter. [18192/20]

Amharc ar fhreagra

Freagraí scríofa

The North South Interconnector is critical to improving the efficient operation of the Single Electricity Market and increasing security of electricity supply across the island of Ireland. It will also help us to move towards 70% renewable electricity. A resilient and well connected energy infra structure is vital for Ireland’s economic well-being and the ability to respond to the future needs of energy consumers.  

EirGrid is the designated Transmission System Operator and its role includes the operation, maintenance and development of the electricity transmission network in Ireland. The construction of the North South Interconnector, and all related procurement activities, is an operational matter for EirGrid and ESB Networks and one in which I have no function. I am advised that due to the very long lead times that can arise in relation to projects of this nature and the benefits of a single joint procurement process to be undertaken and managed by ESB Networks, EirGrid sought approval from the regulators in Ireland and Northern Ireland to commence procurement. Following this approval, in September 2017, ESB Networks commenced a number of procurement processes in relation to the project. In June 2019, ESB Networks awarded a framework contract for the design, test and supply of steelwork in relation to the project. However, under this framework there will be no supply of materials and no critical procurement process for construction will be concluded until the planning process in Northern Ireland is complete.

Barr
Roinn