Duncan Smith
Ceist:124. Deputy Duncan Smith asked the Minister for Education the position regarding a new school project (details supplied); and if she will make a statement on the matter. [25809/20]
Amharc ar fhreagraDáil Éireann Debate, Wednesday - 23 September 2020
124. Deputy Duncan Smith asked the Minister for Education the position regarding a new school project (details supplied); and if she will make a statement on the matter. [25809/20]
Amharc ar fhreagraThe major building project for the new school referred to by the Deputy is at an advanced stage of the tender process. The Design Team has finalised its engagement with the preferred bidder and the preferred bidder is in the process of putting in place the required bond. It is anticipated that the supplementary tender report with the fully executed bond should be received in the Department shortly.
Subject to no issues arising, it is envisaged that construction will commence in the 4th quarter of 2020 with a contract duration of approximately 20 months.