Court Accommodation

Dáil Éireann Debate, Tuesday - 29 September 2020

Tuesday, 29 September 2020

Ceisteanna (321)

Pádraig Mac Lochlainn

Ceist:

321. Deputy Pádraig Mac Lochlainn asked the Minister for Public Expenditure and Reform the surveys the Office of Public Works have carried out on Carndonagh courthouse, County Donegal; and the works required to allow the building to be reopened for the Courts Service at the earliest opportunity. [26439/20]

Amharc ar fhreagra

Freagraí scríofa

While the Office of Public Works has no responsibility for Court buildings, it does provide technical and other services on request to the Courts Service in relation to its buildings.  A Roof Report was prepared by OPW in 2019 and provided to the Courts Service. Previously reports on works required were provided by OPW to the Courts Service in 2007 and 2010.