The building project for the school referred to by the deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.
A Design Team – (Architect, Quantity Surveyor, Civil & Structural Engineer, Mechanical & Electrical Engineer and Project Supervisor for the Design Process) has been appointed and letter of award issued.
The Design Team has commenced work on Stage 1 of Architectural Planning – Site Suitability, Site Surveys and Initial Sketch Scheme.
Upon receipt and review of the Stage 1 Report, my Department will be in contact with the school regarding progression of the project.