190. Deputy John Paul Phelan asked the Minister for Health the timeframe for the completion of construction and the entrance into full operation of the new second cath lab at UHW; and if he will make a statement on the matter. [32190/20]

Amharc ar fhreagra

Freagraí scríofa

The Programme for Government commits to the delivery of a second Cath lab in University Hospital Waterford.  As set out in the HSE’s options appraisal, the preferred option is for a second Cath lab and associated 12 bed day ward (delivering six additional beds) on the roof of the existing Cardiology Department, which will operate five days per week and provide diagnostic services only.

The HSE has advised that funding was allocated in the Capital Plan for the provision of a second Cath lab at University Hospital Waterford and planning permission was received from Waterford City and County Council in January 2020.  The Disability Access certificate was granted on 23rd April 2020. The Fire certificate was granted on 30th June 2020.  Preparation of contract documentation has commenced, and contractor selection is complete subject to a cooling off period. 

Works and schedules were delayed due to COVID-19, however the project went to tender on the 30th September.  As required by OGP, the tender is a 2-stage process for Main and Specialist contractors. This process will take approximately four months. The works to the new Cath laboratory are due to commence in Q1 of 2021 with a proposed 12-month build.  It is anticipated the second Cath laboratory will become fully operational after construction and equipping has been completed.

It is important to recognise, the delivery of capital projects is a dynamic process and is subject to the successful completion of the various approval stages, which can impact on the timeline for delivery.