Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Flood Relief Schemes

Dáil Éireann Debate, Tuesday - 3 November 2020

Tuesday, 3 November 2020

Ceisteanna (474)

Holly Cairns

Ceist:

474. Deputy Holly Cairns asked the Minister for Public Expenditure and Reform the status of all planned and incomplete flood relief and management schemes in County Cork; and if he will make a statement on the matter. [33325/20]

Amharc ar fhreagra

Freagraí scríofa

The following table gives a list of schemes for County Cork and the status of each scheme.

Name of Scheme

Status

Ballinhassig

Scheme at prefeasiblity stage

Ballymakeery/Ballyvourney

Scheme at design/planning stage

Bandon

Construction ongoing but will be substantially complete in 2020.

Bantry

Tender documents for engineering consultant being finalised for issue.

Blackpool

Scheme has been submitted to the Minister for Public Expenditure and Reform for statutory consent under the Arterial Drainage Acts

Carrigaline

Scheme is under review to confirm the technical aspects and viability, and, subject to outcomes, will then progress to Outline Design and Planning.

Clonakilty

Construction ongoing

Douglas(incl Togher culvert)

Construction ongoing

Glashaboy

Scheme has been submitted to the Minister for Public Expenditure and Reform for statutory consent under the Arterial Drainage Acts

Lower Lee (Cork City)

Scheme at design stage prior to submission to the Minister for Public Expenditure and Reform for Statutory consent under the Arterial Drainage Acts

Macroom

Scheme at pre-feasibility stage

Midleton

Scheme at scheme development and preliminary design stage

Skibbereen

Substantially complete

Ballingeary

Scheme to be developed as part of 10-year NDP 2018-2027)

Castlemartyr

Scheme to be developed as part of 10-year NDP 2018-2027)

Castletown Bearhaven

Scheme to be developed as part of 10-year NDP 2018-2027)

Inchigeelagh

Scheme to be developed as part of 10-year NDP 2018-2027)

Inishannon

Scheme to be developed as part of 10-year NDP 2018-2027)

Kanturk

Scheme to be developed as part of 10-year NDP 2018-2027)

Rathcormack

Scheme to be developed as part of 10-year NDP 2018-2027)

Schull

Scheme to be developed as part of 10-year NDP 2018-2027)

Youghal

Scheme to be developed as part of 10-year NDP 2018-2027)

Barr
Roinn