Dáil Éireann Debate, Thursday - 19 November 2020

Thursday, 19 November 2020

Ceisteanna (136)

Neale Richmond

Ceist:

136. Deputy Neale Richmond asked the Minister for Public Expenditure and Reform the amount spent on refurbishments to Stepaside Garda station, Dublin 18; and if he will make a statement on the matter. [37707/20]

Amharc ar fhreagra

Freagraí scríofa

The amount expended to date on this Station by the Office of Public Works is €1,244,780.02 exc. Vat.

This includes €1,141,817.71 exc. Vat for construction costs , €76,099.85 exc. Vat for Consultants fees and €26,862.66 for other costs which include asbestos removal, planning fees, per cent for art allowance, etc. 

The construction final account has been assessed by the Quantity Surveyor and agreed with the Contractor and will be paid after the 12-month Defects Liability Period has elapsed.