Schools Building Projects

Dáil Éireann Debate, Wednesday - 16 December 2020

Wednesday, 16 December 2020

Ceisteanna (206)

Duncan Smith

Ceist:

206. Deputy Duncan Smith asked the Minister for Education the status of the provision of a primary school extension at a school (details supplied); and if she will make a statement on the matter. [44101/20]

Amharc ar fhreagra

Freagraí scríofa

A major extension/ refurbishment project for the school referred to by the Deputy has recently been authorized by my Department to proceed to tender for the appointment of a Building Contractor. The closing date for the completed tender returns is mid-December.

Subject to no significant issues arise during the tender process my Department expects that the project will progress to site in the second quarter of 2021 with a contract duration of approximately 26 months.