The Government announced that additional public health restrictions would apply under Level 5 of the Plan for Living with COVID-19 on 6 January 2021. The additional restrictions required all construction activity to cease from 6pm on Friday 8 January, with a number of exceptions. These measures are set out in The Health Act 1947 (Section 31A - Temporary Restrictions) (Covid-19) (No. 10) (Amendment) Regulations 2021.
While my Department is responsible for social housing, with regard to private housing development the Regulations provide that housing and construction works ongoing on 8 January can continue where the works required to render the property capable of occupation are scheduled for completion by 31 January 2021.
The Government will continue to review the arrangements applying to construction as part of the overall Plan for Living with COVID-19.