Schools Building Projects

Dáil Éireann Debate, Wednesday - 3 February 2021

Wednesday, 3 February 2021

Ceisteanna (364, 365)

Donnchadh Ó Laoghaire

Ceist:

364. Deputy Donnchadh Ó Laoghaire asked the Minister for Education the progress on the building of a permanent school building for a school (details supplied); the status of the tendering process; and the timeframe for the completion of the build. [5184/21]

Amharc ar fhreagra

Donnchadh Ó Laoghaire

Ceist:

365. Deputy Donnchadh Ó Laoghaire asked the Minister for Education the costs of providing prefabricated accommodation for a school (details supplied); the length of time she expects the teachers and students to be accommodated in the prefabricated buildings; and the reason there has been a delay in providing a permanent school building for the school. [5185/21]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 364 and 365 together.

The school building project referred to by the Deputy is being delivered under my Department’s Design and Build Programme.  The application for planning permission for the permanent school was lodged in December 2018 and the notification of the Decision to Grant Permission (subject to 18 no. conditions) was received on 13 June 2019. Two of these conditions were subsequently the subject of a first party appeal by my Department to An Bord Pleanála (ABP). The decision on this appeal was received on 4 February 2020.

In early December 2019, the tender notice was published for the first bundle of projects in the first stage of a two stage tender process to establish a new Framework of Design and Build Contractors. It was not possible for the school in question to be included in the first bundle of projects as the decision of ABP was not received until February 2020.

The school is due to be included in the next bundle of projects and it is expected to go to tender in Quarter 2 of 2021. This exact timeframe will be dependent on the completion of phase 2 of the current tender process to establish the Framework of Contractors which is expected to conclude in Quarter 1 of 2021. 

Pending delivery of the permanent building project, my Department will continue to address the interim accommodation needs of the school on its permanent site and the school authorities will be kept informed of progress.

Since 2016, the total spend on the provision of interim accommodation is some €4.5m including some €1.5m of expenditure related to site works for the interim accommodation which will also facilitate the construction of the permanent school building.

Barr