Flood Relief Schemes

Dáil Éireann Debate, Wednesday - 28 April 2021

Wednesday, 28 April 2021

Ceisteanna (318)

Joe Carey

Ceist:

318. Deputy Joe Carey asked the Minister for Public Expenditure and Reform further to Parliamentary Question No. 101 of 21 April 2021, if he will report on progress to provide flood relief works specifically at Springfield, Clonlara, County Clare; and if he will make a statement on the matter. [21845/21]

Amharc ar fhreagra

Freagraí scríofa

Clare County Council (CCC) is the contracting authority in relation to the proposed flood relief scheme in Springfield/Clonlara, with funding provided by the Office of Public Works (OPW). The current position is as follows: 

CCC has been in contact with land owners affected by the proposals and has consulted with local residents and relevant statutory bodies. The Council submitted the works for planning permission, which was granted by An Bord Pleanala in November 2020. Since then detailed design has been ongoing and is now substantially complete, with some final additional Ground Investigations ongoing, which are to be completed and reviewed in advance of the projected construction start date of Q2 this year, with the construction works being carried out by the OPW as contractor for the local authority. 

Barr
Roinn