Dáil Éireann Debate, Tuesday - 13 July 2021

Tuesday, 13 July 2021

Ceisteanna (206)

Alan Dillon

Ceist:

206. Deputy Alan Dillon asked the Minister for the Environment, Climate and Communications the efforts that have been undertaken by his Department to accelerate the roll-out of the National Broadband Plan in a location (details supplied); the engagement that has taken place with National Broadband Ireland on accelerating the roll-out; and if he will make a statement on the matter. [37498/21]

Amharc ar fhreagra

Freagraí scríofa

The Question refers to a premises located in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map which is available on my Department's website www.broadband.gov.ie. The AMBER area represents the area to be served by the network to be deployed under the NBP State led intervention. I appreciate people's frustration when they are living so close to a fibre network but cannot get a connection to that network, particularly given the heightened importance of connectivity during the Covid-19 pandemic. The NBP will ensure that in all such cases a future proofed high speed broadband network will be built to serve these premises and work to deliver on this is underway. 

I am advised by National Broadband Ireland (NBI) that, as of 8 July, over 233,000 premises across all counties have been surveyed. Surveys are complete or underway in County Mayo including in the areas of Aghagower, Ballyhean, Breaghwy, Burren, Castlebar, Clogher, Cloonkeen, Croaghmoyle, Islandeady, Killavally, Manulla, Pontoon, Strade, Tawnynagry, Turlough, Drumsheen, Bunnyconnellan, Ballina Town, Carrowntreila, Ardagh, Campbells Crossroads, Rosserk, Shanvoley, Derryhick, Kilhale, Tawnylaheen, Turlough, Ballyvary, Keeloges, Castlebar Town, Rinnaseer, Bellaburke, Killawullaun Mountain, Carn, Carnacon, Ballyglass, Belcarra, Balla and Ringarraun. Surveys are commencing in the areas of Newport, Carrowbeg, Inishgort, Inishcottle, Myna, Fahy, Ashbridge, Glenisland, Srahmore, Glenhest, Comploon, Slogger and Tawnameeltoge. I am advised that pre-build works have commenced in areas around Castlebar and Ballina.

Further details are available on specific areas within County Mayo through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. NBI also has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.

While substantial progress has been made to date, the Covid-19 pandemic has had an impact on the delivery of the fibre network resulting in delays to aspects of the programme. Impacts include challenges with mobilisation of key contractors, restrictions on operations, supply chain and logistic delays (both nationally and internationally). Covid-19 has affected the recruitment of key personnel as NBI and its contractors scale up including challenges associated with on-boarding and training people. Inevitably, like many other organisations, NBI and contractor staff are at risk of contracting Covid 19 or may have to restrict their movements as a result of being a close contact posing further challenges. The full extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in so far as possible.

The Programme for Government commits to seek to accelerate the roll out of the National Broadband Plan. The Department is currently engaging with NBI to explore the feasibility of accelerating aspects of the NBP rollout to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19. As part of that work NBI is engaging with all current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners where such options could also speed up the build process. I am advised that these discussions are progressing well.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 8 July, 335  BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and the Department of Education for school BCPs. BCP’s are connected at Belderrig Community and Research Centre, Bofeenaun Community Centre, Taugheen Community Centre, Kilmovee Community Centre, Belderrig Community and Research Centre, Clare Island Community Centre, Keel Community Centre, Killaser Community Centre, Islandeady Community Centre, Finny Community Centre, Cushlough Community Centre, Carrowkennedy and The Black Tom Freeman Sport and Community Amenities Centre, Aghamore (located 10.8km from the premises referred to). Further details can be found at https://nbi.ie/bcp-locations/.

Saint Coleman's National School, Scoil Néifinn, Rathbane National School, Midfield National School, Meelick More National School, Kinaffe National School, Gortskehy National School, Facefield National School, Errew National School, Cloghans National School, Shraigh National School, Rathnamagh National School, Dooagh National School, The Brae Valley National School, Dookinella National School and Tavraun Central National School have been installed by NBI for educational access. My Department continues to work with the Department of Education to prioritise schools with no high speed broadband, within the Intervention Area, for connection over the term of the NBP. In this regard, an acceleration of this aspect of the National Broadband Plan was announced in December which will see some 679 primary schools connected to high speed broadband by 2022, well ahead of the original target delivery timeframe of 2026. Further details are available on the NBI website at https://nbi.ie/primary-schools-list/.