2598. Deputy Dessie Ellis asked the Minister for Health the variance to the budget by expense category of the new national children's hospital in tabular form in view of the reports that it is set to cost €1.7 billion, up from the original estimated cost of circa €400 million; and if he will make a statement on the matter. [38304/21]

Amharc ar fhreagra

Freagraí scríofa

The previous Government approved an investment decision of €1.433bn for the capital project, which is €450m more than advised to Government in April 2017. This includes all of the capital costs for the main hospital at St James's Hospital campus, the two Outpatient Departments and Urgent Care Centres at Connolly Hospital, Blanchardstown and Tallaght University Hospital campuses, equipment for the three sites, and the construction of the carpark and retail spaces.

In addition to the capital project there is a broader programme of activity including new ICT and electronic health record development, and the integration and transfer of the services of the three children’s hospitals to the new sites which will bring a total overall programme cost of €1.73bn.

There are several items not included in this figure as there was no price certainly for them and nor can there be for the duration of the project, including excessive construction inflation (>4%) and the impact of Covid-19.

The table below outlines in tabular format the variance to the provisional budget on 2017 to the current budget, approved in 2018.

Table 21: Escalation in costs of the National Children's Hospital by Item 2017-2018govacc.per.gov.ie/wp-content/uploads/Periodic-Report-No.6-Final-Oct-2018-May-2019.pdf

Item

2017 Costs €m

2018 Costs €m

Decant

16

14.5

Aspergillus

6.8

5.8

Main NCH

637

890

Less Value Engineering

-66

Net Main NCH construction

571

890

Outpatient & Urgent Care Centres

38

53.4

Sub Total

631.8

963.7

VAT

85.3

130.1

Gross Construction Costs

717.1

1093.8

Equipping

71.6

87.9

Planning

14.9

13.6

Design Team Fees

43.7

71.3

Risk/Contingency

39

51.3

NPH Project costs

52

66.04

Other Costs Sub Total

221.1

290.1

VAT (excluding construction)

44.7

49

Sub Total Gross Other Costs

265.9

339.1

Capital Build Sub Total

983

1.433bn

Children's Research & Innovation Centre

86

86

ICT

88

97

Children's Hospital Integration Programme

86

86

Electronic Healthcare Record

52

52

Mater Campus

40

40

Sub Total

284

293

Grand Total

1.26bn

1.7bn