National Broadband Plan

Dáil Éireann Debate, Thursday - 4 November 2021

Thursday, 4 November 2021

Ceisteanna (56)

James O'Connor

Ceist:

56. Deputy James O'Connor asked the Minister for the Environment, Climate and Communications the status of the National Broadband Ireland roll-out project for the Youghal and Killeagh area; and if he will make a statement on the matter. [53710/21]

Amharc ar fhreagra

Freagraí scríofa

The Question refers to areas located in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map which is available on my Department's website www.broadband.gov.ie. The AMBER area represents the area to be served by the network to be deployed under the NBP State led intervention.

I appreciate people's frustration when they are living so close to a fibre network but cannot get a connection to that network, particularly given the heightened importance of connectivity during the Covid-19 pandemic. The NBP will ensure that in all such cases a future proofed high speed broadband network will be built to serve these premises and work to deliver on this is underway.

I am advised by National Broadband Ireland that, as of 27 October 2021, almost 26,000 premises in County Cork have been surveyed. In total, over 272,000 premises in the Intervention Area across all counties have been surveyed, with over 115,000 premises under construction across 30 Deployment areas. Retail service providers are actively selling on the NBI network with over 30,000 premises available to order and pre-order in Counties Carlow, Cavan, Clare, Cork, Galway, Kerry, Limerick, Monaghan, Roscommon, Tipperary, and Wicklow. This includes over 4,500 premises in County Cork.

Surveys are also complete in County Cork in the Deployment Areas of Carrigaline, Midleton, Youghal, Templemartin and Tallow. Main build work are currently underway in Midleton and Youghal and are complete in Carrigaline. There are 3,500 premises in the Youghal Deployment area which includes Kileagh and NBI anticipates premises will be passed and available for connection in Youghal in H1, 2022. Further details are available on specific areas within County Cork through the NBI website which provides a facility for people living within the intervention area to register their interest in being provided with deployment updates at www.nbi.ie.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 27 October, 386 BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and the Department of Education for school BCPs. BCPs are installed in County Cork at Ballydaly Community Hall, Aubane Community Centre, Mealagh Valley Community Centre, Courtbrack Community Centre, Laharn Heritage Centre, Ballindangan Community Centre, Clogagh Community Hall, Aghabullogue Community Centre, Castletownkenneigh Community Centre, The Old Schoolhouse, Bere Island Heritage Centre, Coláiste Phobal Cléire, Lissavard Community Centre, Whitechurch Community Centre, Glash Community Centre, T.O. Park Labbamollaga and Sherkin Island Community Hall.

Templebrady National School, Ballycroneen National School, Clogagh National School, Educate Together Carrigaline, Ringaskiddy Lower Harbour National School, Scoil Naomh Fionan Na Reanna, Ballygarvan National School and Shanbally National School have been installed by NBI for educational access. My Department continues to work with the Department of Education to prioritise schools with no high speed broadband, within the Intervention Area, for connection over the term of the NBP. In this regard, an acceleration of this aspect of the National Broadband Plan was announced in December which will see some 679 primary schools connected to high speed broadband by 2022, well ahead of the original target delivery timeframe of 2026.