Schools Building Projects

Dáil Éireann Debate, Thursday - 10 March 2022

Thursday, 10 March 2022

Ceisteanna (91)

Brian Stanley

Ceist:

91. Deputy Brian Stanley asked the Minister for Education the funding that is designated to providing a new building for a school (details supplied). [13312/22]

Amharc ar fhreagra

Freagraí scríofa

The major building project for Kolbe Special School in Portlaoise is included in my Department’s Construction Programme which is being delivered under the National Development Plan.

The €4.4 billion funding envelope for the schools capital programme under Project Ireland 2040 provides a basis for a strong rollout of projects including in respect of Kolbe Special School.

The project is currently at an advanced stage of architectural planning Stage 2b – Detailed Design, which includes the application for all statutory consents, including Planning Permission, Disability Access Certification and Fire Safety Certification and also the preparation of tender documentation.

Planning Permission has recently been granted. The Disability Access Certification has also been granted and the application for Fire Safety Certification is with the Local Authority and their response is pending.

The Design Team is currently working on completion of the Tender documents and finalisation of the Stage 2(b) report which will then be submitted to my Department for review and approval.

To expedite the project the prequalification of contractors is being carried out in parallel with the completion and review of Stage 2(b) and the Design Team have been authorised to commence that process just last week.

Upon receipt, review and approval of the Stage 2b submission, completion of the prequalification of contractors, and once the Design Team are satisfied that their tender documents are in order and comply with all Departmental and Building Regulation requirements the project for Kolbe Special School can be progressed to tender and award of contract.

A Tender stage normally takes between 6 to 8 months subject to no issues arising.

My Department is committed to delivering this project as quickly as possible.