Departmental Schemes

Dáil Éireann Debate, Thursday - 7 April 2022

Thursday, 7 April 2022

Ceisteanna (141)

Aindrias Moynihan

Ceist:

141. Deputy Aindrias Moynihan asked the Minister for the Environment, Climate and Communications the progress that is being made in reducing the processing times and commencement of works under the free energy upgrades, warmer homes scheme; and if he will make a statement on the matter. [18744/22]

Amharc ar fhreagra

Freagraí scríofa

The Better Energy Warmer Homes Scheme delivers free energy upgrades for eligible homeowners in low-income households who are most at risk of energy poverty. It is administered by the Sustainable Energy Authority of Ireland (SEAI). Since the start of the scheme in 2000, over 145,000 free upgrades have been supported. In 2021, the average cost of the energy efficiency measures provided per household had increased significantly to €17,100.There are currently just over 6,900 homes awaiting works on the Better Energy Warmer Homes Scheme work programme. This includes homes that are: - Awaiting the initial survey of their home;

- Have completed an initial home survey and are awaiting allocation to a contractor;

- Have been allocated to a contractor for works; or,

- Currently undergoing works.Activity under the Scheme, and the associated expenditure, were significantly impacted in both 2020 and 2021 by the COVID pandemic. SEAI data indicates that for homes completed in 2021, the average cycle time from application to completion was approximately 26 months. While this delay was largely driven by Covid related issues, the deeper measures being provided under the Scheme since 2018, also involve more substantive works. In order to reduce this timeline to completion, the following key actions are being taken:

- The budget, at €109 million, is nearly three times the 2021 outturn (€38 million) and funding has also been sought through the European Regional Development Fund;

- The number of homes retrofitted under the scheme are due to increase from 177 per month in 2021 to 400 per month in 2022, this is a top priority in SEAI's work programme;

- SEAI has allocated additional staff for the Better Energy Warmer Homes Scheme;

- SEAI is working to increase contractor output through active contract engagement and management.Works under the Scheme recommenced in line with activity in the residential construction sector and activity did ramp up again towards the end of last year. Based on the foregoing, SEAI target clearing the homes currently on the waiting list in approximately 18 months.

Question No. 142 answered with Question No. 126.