My Department issued Stage 3 Pre-tender Approval for this project on 6 August 2021 to the Council. It is a matter for the relevant Approved Housing Body (AHB) and Limerick City and County Council to advance the project.
Cost plans associated with this project are not available due to commercial sensitivity as this project is out to tender.
Under the 75 week timeline for projects under the Capital Assistance Scheme, a Stage 4 submission including a tender report was due into my Department by 5 November 2021, but this has not been received to date. The Council and AHB should submit this to my Department as soon as possible in order for this project to be progressed.