Schools Building Projects

Dáil Éireann Debate, Thursday - 2 June 2022

Thursday, 2 June 2022

Ceisteanna (279, 280)

Seán Sherlock

Ceist:

279. Deputy Sean Sherlock asked the Minister for Education if she will publish the schematics and plans for a project (details supplied).; and if she will make a statement on the matter. [28716/22]

Amharc ar fhreagra

Seán Sherlock

Ceist:

280. Deputy Sean Sherlock asked the Minister for Education if she is in receipt of a timeline for construction of a project (details supplied). [28717/22]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 279 and 280 together.

The Letter of Acceptance (LOA) issued to the preferred tenderer on the 18th May 2022 commencing the school building contract for the school referred to by the Deputy. 

The construction programme underpinning the contracts will be provided by the Contractor shortly and my Department will advise the schools as soon as possible in this regard.

The plans for the project were shared with the school prior to submission of the planning application and may also be viewed on the Council’s website – www.corkcoco.ie .

Question No. 280 answered with Question No. 279.