The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which includes the islands and covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools. The deployment plan forecasts construction commenced in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.
I am advised by National Broadband Ireland (NBI) that, as of 22 January 2021, over 166,000 premises across all counties have been surveyed under the National Broadband Plan. Surveying is the first step towards delivering the new fibre network and involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This informs design solutions for provision of the fibre network to each and every premises in the surveyed area and leads to detailed designs. Survey data is also needed to initiate pre-works which pave the way for the deploying of fibre. I understand that surveying is expected to commence in a number of islands later this year.
Further details are available on specific areas through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. I am advised that NBI is working to provide more detail on its website, with a rolling update on network build plans. NBI also has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.
Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 30 January, 260 BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and by the Department of Education for schools. Further details can be found at https://nbi.ie/bcp-locations/.
My Department continues to work with the Department of Education to prioritise schools with no high speed broadband as part of the BCP initiative, within the Intervention Area, for connection over the term of the NBP which includes the Islands. In this regard, an acceleration of this aspect of the National Broadband Plan was announced in December which will see some 679 primary schools connected to high speed broadband by 2022, well ahead of the original target delivery timeframe of 2026. Further details are available on the NBI website at https://nbi.ie/primary-schools-list/.
The following table sets out the BCP sites that have been installed, connected or are in planning on the Islands.
Site Name
|
Eircode
|
County
|
Installed
|
Connected
|
School
|
CLARE ISLAND COMMUNITY CENTRE
|
F28KP99
|
MAYO
|
Yes
|
Yes
|
-
|
BERE ISLAND HERITAGE CENTRE
|
P75W660
|
CORK
|
Yes
|
Yes
|
-
|
SHERKIN ISLAND COMMUNITY HALL
|
P81AE02
|
CORK
|
Yes
|
In Planning
|
-
|
COLÁISTE PHOBAL CLÉIRE
|
P81P627
|
CORK
|
Yes
|
In Planning
|
-
|
SCOIL CAOMHAIN
|
H91C967
|
GALWAY
|
Yes
|
In Planning
|
Yes
|
COMHAR NA NOILEÁN
|
H91D27X
|
GALWAY
|
Yes
|
Yes
|
-
|
INISHBOFIN COMMUNITY CENTRE
|
H91TC6C
|
GALWAY
|
In planning
|
In Planning
|
-
|
KILRONAN LIBRARY
|
H91WN93
|
GALWAY
|
Yes
|
In Planning
|
-
|
Cable Station
|
V23H685
|
KERRY
|
Yes
|
Yes
|
-
|
TORY CO-OP
|
F92FD66
|
DONEGAL
|
Yes
|
Yes
|
-
|
CHAPELTOWN
|
V23H240
|
KERRY
|
Yes
|
Yes
|
-
|