Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Flood Risk Management

Dáil Éireann Debate, Wednesday - 15 February 2023

Wednesday, 15 February 2023

Ceisteanna (78)

Holly Cairns

Ceist:

78. Deputy Holly Cairns asked the Minister for Public Expenditure, National Development Plan Delivery and Reform when the Skibbereen flood defence scheme will be complete, given current delays are holding up necessary road works on the N71. [7757/23]

Amharc ar fhreagra

Freagraí scríofa

The Skibbereen Flood Relief Scheme was substantially completed on 6th June 2019.

Planning for the operation and maintenance of the scheme is ongoing in conjunction with Cork County Council, who will act as agents of the OPW in carrying out the statutory operation and maintenance of the scheme. A small number of works to address elements identified during construction and since completion of the scheme works, which were outside the main construction contract, remain to be completed and are being progressed in separate works packages.

A length of flood defence wall upstream of the footbridge in the town centre remains to be constructed, which will facilitate flood defence at a high level (for relatively rare floods) for the adjacent apartments and the town centre, as well as for a proposed future public walkway, being proposed by Cork County Council. Cork County Council is continuing to engage with the owners of a property located on Levis Quay to gain the relevant consents to construct a river walkway when completing a section of sheet piled flood protection wall on the left bank of the River Ilen. It is expected that the cost for this remaining work will be shared between Cork County Council and the OPW.

In addition, some drainage works on the N71 Cork Road, which fall outside the remit of the main scheme, have subsequently been identified as being necessary. These works are being progressed in conjunction with Transport Infrastructure Ireland (TII) and some funding is being provided by the OPW under the Minor Flood Mitigation Works & Coastal Protection Scheme.

As part of the main flood relief scheme, follow-on works are being progressed at two culverts, on Mill Road. In addition, discrete sections of rock revetments are to be installed.

All of the above works are programmed to take place in 2023.

Barr
Roinn