Broadband Infrastructure

Dáil Éireann Debate, Tuesday - 14 May 2024

Tuesday, 14 May 2024

Ceisteanna (131)

Bernard Durkan

Ceist:

131. Deputy Bernard J. Durkan asked the Minister for the Environment, Climate and Communications the steps he can take to speed up the provision of broadband services through the medium of fibre-optics throughout County Kildare, with particular reference to known blackspots; and if he will make a statement on the matter. [21831/24]

Amharc ar fhreagra

Freagraí scríofa

Ireland's Digital Connectivity Strategy, published by my Department, sets ambitious targets, which include providing a Gigabit network to all households and businesses in Ireland by 2028 and access to 5G in all populated areas by 2030.

The National Broadband Plan (NBP) is the government's initiative to deliver high speed broadband services to all premises in Ireland.

National Broadband Ireland (NBI) are connecting circa 4,000 homes each month. NBI expect to have passed in excess of 300,000 premises by the end of 2024 with circa 120,000 premises passed each year thereafter until the end of deployment.

I am advised by NBI that, over 243,000 premises are passed across 26 counties and available for immediate connection. Over 80,200 premises are already connected to the National Broadband Plan high-speed broadband network. In the Deputy’s own county of Kildare over 5,900 premises are passed with a high-speed fibre broadband network which represents 40% of the premises within the Intervention area. At the end of April 2024, 1,996 premises are now connected in Kildare which represents a take up rate of 33%.

Further details are available on specific areas within County Kildare and can be monitored via nbi.ie/reps.

Along with the NBP intervention contract, progress is being made by commercial operators’ in expanding their next generation networks throughout the State and ensuring the targets set out in the Digital Connectivity strategy are achieved.

My Department is aware through engagement with various stakeholders, including commercial operators and ComReg, of the possibility that it may not be viable for commercial operators to reach all premises in urban areas to deliver on EU and National Targets. These are areas currently not within the scope of the National Broadband Plan.

An extensive mapping exercise will be required taking account of commercial deployments which are currently being rolled out, to identify the scale of this potential problem including identifying individual Eircode's impacted. My Department are currently engaged with ComReg on this exercise.

If it emerges that the market cannot deliver on EU and National Connectivity Targets, the Department will consider appropriate public policy tools required to ensure those targets are achieved.