Bill entitled an Act to provide for emergency measures for electricity generation development to ameliorate and protect security of supply of electricity in the State because exceptional circumstances have arisen in the market for that supply and further because of the situation in Ukraine; for disapplication of the Planning and Development Act 2000 for the purpose of such development; for such development to be exempt from the provisions of Directive No. 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment amended by Directive 2014/52/EU of the European Parliament and of the Council of 16 April 2014, in accordance with Article 2(4) of that Directive; for application of arrangements for the alternative assessment of such development for the purposes of that Directive and the appropriate assessment of such development for the purposes of Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora, and for the co-ordination of such assessments; and to provide for related matters.
Last updated: 29 Oct 2022
History of this Act
The Bill has been signed into law by the President.
29 Oct 2022
Dáil Éireann
Seanad Éireann
-
Dáil First Stage
20 Oct 2022
Dáil First Stage
The Bill is initiated or presented to the House
20 Oct 2022
Completed
-
Dáil Second Stage
20 Oct 2022
Dáil Second Stage
The general principles of the Bill are debated
20 Oct 2022
Completed
-
Dáil Third Stage
26 Oct 2022
Dáil Third Stage
The Bill is examined section by section and amendments may be made
(Also known as Committee Stage)26 Oct 2022
Completed
-
Dáil Fourth Stage
26 Oct 2022
Dáil Fourth Stage
Amendments arising out of Committee Stage are considered
(Also known as Report Stage)26 Oct 2022
Completed
-
Dáil Fifth Stage
26 Oct 2022
Dáil Fifth Stage
Final statements on the Bill are made and it is set down for Second Stage in the Seanad
(Also known as Final Stage)26 Oct 2022
Completed
-
Seanad First Stage
n/a
Seanad First Stage
The Bill is deemed to have passed Seanad First Stage
n/a
Completed
-
Seanad Second Stage
26 Oct 2022
Seanad Second Stage
The general principles of the Bill are debated
26 Oct 2022
Completed
-
Seanad Third Stage
27 Oct 2022
Seanad Third Stage
The Bill is examined section by section and amendments may be made
(Also known as Committee Stage)27 Oct 2022
Completed
-
Seanad Fourth Stage
27 Oct 2022
Seanad Fourth Stage
Amendments arising out of Committee Stage are considered
(Also known as Report Stage)27 Oct 2022
Completed
-
Seanad Fifth Stage
27 Oct 2022
Seanad Fifth Stage
Final statements on the Bill are made
(Also known as Final Stage)27 Oct 2022
Completed
-
Enacted
29 Oct 2022
Enacted
The Bill is signed into law by the President
29 Oct 2022
Completed
29 Oct 2022
An tAcht um Fhorbairt (Giniúint Éigeandála Leictreachais), 2022
29 Oct 2022
Development (Emergency Electricity Generation) Act 2022
20 Oct 2022
As initiated
Development (Emergency Electricity Generation) Bill 2022
Amendments
27 Oct 2022
Committee Stage
Numbered List [Seanad]
25 Oct 2022
Committee Stage
Numbered List [Dáil]
This list of debates may not be complete. You can also search directly for this Bill within the Debates section.
Debates
27 Oct 2022
Seanad Éireann
Development (Emergency Electricity Generation) Bill 2022: Committee and Remaining Stages
27 Oct 2022
Seanad Éireann
Development (Emergency Electricity Generation) Bill 2022: Second Stage
26 Oct 2022
Dáil Éireann
Development (Emergency Electricity Generation) Bill 2022: Committee and Remaining Stages
26 Oct 2022
Dáil Éireann
Development (Emergency Electricity Generation) Bill 2022: Second Stage