Ceisteanna—Questions. Oral Answers. - Dublin-Sligo Telephone Cable.

asked the Minister for Posts and Telegraphs if he will state when the co-axial cable connecting Dublin and Sligo will be completed, and when sections will be in operation for calls to towns along the route.

It is estimated the entire scheme will be completed in about 18 months and that the following main sections of it will come into service within the periods indicated:

Dublin—Mullingar

4 months.

Dublin—Athlone

8 months.

Mullingar—Athlone

Boyle—Carrick-on-Shannon

10 months.