342.

asked the Minister for the Environment the priority list for sewerage schemes in villages in County Clare; and when work is likely to commence.

The following is the position regarding each of the village sewerage schemes on Clare County Council's priority list:

Village

Priority in Clare County Councils List

Present position of proposed Sewerage Schemes

Kilfenora

1

Tenders under examination. Additional information awaited from local authority.

Mount Shannon

2

Contract Documents under consideration.

Feakle

3

Contract Documents under consideration.

Broadford

4

Contract Documents under consideration.

Quin

5

Tenders under examination. Additional information awaited from local authority.

Killaloe

6

Contract re-advertised by local authority.

Clonlara

7

Preliminary Report being revised.

Carrigahalt

8

Contract Documents under consideration.

Miltown Malbay

9

Preliminary Report under consideration.

Doonbeg

10

Contract Documents being prepared.

Kilkishan

11

Contract Documents under consideration.

Cooraclare

12

Contract Documents under consideration.

Quilty

13

Contract Documents under consideration.

O'Briens Bridge

14

Preliminary Report under consideration.

Mullagh

15

Contract Documents under consideration.

O'Callaghans Mills

16

Contract Documents under consideration.

Lisdoonvarna

17

Preliminary Report submitted. Additional information awaited from local authority.

Clarecastle

18

Contract Documents being prepared.

I cannot say when I may be in a position to convey decisions to the local authority regarding their proposals for the various schemes.